PMIS Project Change Management

License: LGPL-3 PMISuite/operations Version: 18.0

Review and authorize changes to a sale Bill of Quantities, then trace the approved revision to the revised items and the relevant temporary Situations. Use initiative charters to document the business case and stakeholder impacts for related commercial change requests.

Slovenščina

Download the Organizational Change Management manual (PDF)

Illustrated user manual

Table of contents

Configuration

Install PMIS Project Change Management with PMIS Bills of Quantities. Grant PMIS Change User to participants alongside the existing PMIS access they need for projects, BoQs, and Situations. Grant PMIS Change Configuration Manager to users who configure approval roles. On the PMIS project, assign separate internal and commercial approvers and a verifier. Enable Require Customer Authorization when the contract requires evidence of customer approval for these changes.

Initiatives

Open Change Initiatives in Operations. Choose the company and, when the initiative applies to one project, select that project when creating it. Assign a sponsor and owner. They can record the problem, baseline, target outcome, and target behaviors on the Charter tab.

Use Stakeholder Impacts to describe how each group is affected, record concerns and an engagement approach, and assign an action owner and review date. Use the Commercial Change Requests button to link existing requests in the same company and, for a project-scoped initiative, in the same project. Each request can belong to one initiative. Participants see linked requests they already have permission to read. Links follow the request through new revisions and closure.

On Readiness, record checks and their evidence. Use Communication and Training to plan briefings and training and record their outcomes. The assigned sponsor can authorize or hold a pilot. Authorization requires at least one readiness check and evidence that every critical blocker is ready. Readiness is locked while authorization is active. Sponsor decisions remain available in the initiative's history.

Capture Pilot Feedback from each cohort. Record Adoption Metrics by measurement period and compare observed use with the target. Assign and track Reinforcement Actions with links to supporting evidence and a record of the outcome.

Plan Rollout Waves by cohort, with an owner, start date, and rollback plan. The sponsor can scale, hold, or roll back each wave and record the evidence for the decision. Schedule Sustainment Reviews to track whether the new way of working holds and record any follow-up.

Track Benefits against a baseline and target, with an owner, measurement method, and evidence. The sponsor can close the initiative after operational handover or rollback. Use Change Portfolio to compare wave and benefit counts by project and lifecycle state.

Workflow

  1. Open Changes on the project or sale BoQ. Create a request and open its current revision.

  2. Add the proposed BoQ items, amendments, or omissions, and describe the reason and schedule impact. Submit the revision for review.

  3. Review assigned proposals from My Change Reviews. The internal approver reviews first. The commercial approver records any required customer decision and signed evidence.

  4. Start implementation before editing the live BoQ. Apply the change using the existing BoQ workflow. Use Evidence on each impact to link the resulting item and any relevant draft Situation lines. For omissions, record the source item with its quantity reduced to zero. For impacts without a Situation line, record the disposition using No Situation.

  5. Ask the project verifier to verify the resulting items and the Situation disposition. Close the verified revision.

A returned proposal gets a new draft revision. Approved changes can be revised before implementation starts. Use a follow-up request for changes to work already under implementation. A Situation link records attribution. Situation valuation, acceptance, and invoicing follow the existing Operations workflow.

An in-place amendment or omission applies to items that have not entered a submitted or certified Situation. Use the agreed commercial adjustment route for changes to previously valued items.

Bug Tracker

Bugs are tracked on PMISuite Repository Issues. In case of trouble, please check there if your issue has already been reported. If you spotted it first, help us smashing it by providing a detailed and welcomed feedback.

Credits

Authors

Contributors

  • Matjaž Mozetič

Maintainers

LUXIM MATMOZ

Current maintainer:

sysadminmatmoz

Luxim is an independent R&D and deployment company focused on solving complex problems in the Odoo ecosystem.

Odoo Community Association

Luxim is an active member of OCA (Odoo Community Association).