PMIS Risk Management user manual
Module README · Operations module index · Slovenski priročnik
Table of contents
- Set up the Risk Team
- Log and score a risk
- Assign and complete mitigation
- Review and reassess exposure
- Close or reopen a risk
- Use the register and check access
- Manage risks on the Risk Board
- Examine exposure in the Risk Matrix
- Prepare and print a project review
- Record assessments and follow trends
- Escalate and review high residual risks
- Record a materialized risk and its follow-up
- Link an existing OCA record
- Review follow-ups before closing a risk
Set up the Risk Team
- Install PMIS Risk Management. It uses the projects and sites from PMIS Bills of Quantities.
- Give internal contributors PMIS Risk User. Give people who approve closure PMIS Risk Reviewer, which includes the user role.
- As a Sales administrator, open Bills of Quantities → Operations → Projects. Open the project, add contributors and reviewers to Risk Team, and save.
- Make sure each team member can select the project's company. Include the people who will own risks or receive mitigation actions and review activities.
Log and score a risk
- Open Risk Register from the app menu or click Risks on a PMIS Project. Click New.
- Enter a title, select the Project, and optionally select one of its Sites. The project is fixed after saving.
- Choose a Category and describe the cause, possible event, and impact. For example, late panel dispatch could delay East Wing installation.
- Set the Owner and Next Review. New risks start Open. Next Review defaults to seven days from today.
- Select Likelihood and Impact under Initial Assessment, then save. In this example, Likely (4) × Severe (5) gives an initial score of 20.
| Rating | Likelihood | Impact |
|---|---|---|
| 1 | Rare | Negligible |
| 2 | Unlikely | Minor |
| 3 | Possible | Moderate |
| 4 | Likely | Major |
| 5 | Almost Certain | Severe |

Figure 1. Training Pavilion's East Wing risk has an initial score of 20 and a next review date of January 15.
Assign and complete mitigation
- Open Mitigation Actions and select Add a line.
- Enter the action, choose a project team member as Assignee, and set the Due Date. Save the risk.
- When the work is complete, enter Completion Evidence, select Done, and save. Evidence can be a brief record of what you verified.

Figure 2. The backup supplier action is marked done and its completion evidence appears on the same row.
Review and reassess exposure
The owner receives a Risk Review activity due on the Next Review date. Find it in the risk's chatter, in the register's activity column, or in your Odoo activities. Changing the owner or date updates the pending activity.
- Inspect open actions and the evidence for completed actions.
- Enter both ratings under Residual Assessment. A score of 0 indicates that the residual risk is awaiting assessment. Here, Unlikely (2) × Moderate (3) gives 6.
- Set the state to Monitoring while tracking the remaining exposure. Enter the next review date and save.

Figure 3. The updated assessment records a residual score of 6 and moves Next Review to January 22.
Close or reopen a risk
As a PMIS Risk Reviewer on the project, confirm that both residual ratings are present. Get residual acceptance first when the score meets the company threshold. Set State to Closed, enter a Closure Reason, and save. Odoo removes the pending automatic review activity. To resume monitoring, set the state to Open or Monitoring, choose the next review date, and save to create a new reminder.

Figure 4. The reviewer records the reason for closing the supplier risk.
Use the register and check access
Use the list to scan owners, scores, states, and review dates. Use the pivot to count visible risks by project and state. Use Open Risks, Overdue Reviews, Overdue Mitigation, and High Residual Exposure to focus the list. High residual exposure starts at the company threshold.

Figure 5. The Pavilion team member sees the supplier risk and its Risk Review activity in the register.
Both risk roles require project membership and an active company to open the risk or its actions, including from a saved link. Removing someone from Risk Team clears their pending risk activities. Reassign their open risks to a current team member to restore reminders.

Figure 6. The Depot reviewer sees the forklift risk. The Pavilion risk is visible to its own team.
Manage risks on the Risk Board
- Open Risk Register → Risk Board. Open, Monitoring, and Closed each have a column. Every card shows its project, optional site, owner, initial score, residual score, next review date, and overdue mitigation count.
- Use Project in the sidebar to narrow the board, then select one or more Site checkboxes. A site selection hides project-wide risks. Clear the site checkboxes to include them again.
- Scan for a red Overdue mitigation count. An action counts as overdue when it is still unfinished and its due date has passed. The count can remain positive on a closed risk when actions are still outstanding.
- Click a card to open the risk form. Update the State there and save to move the card. A PMIS Risk Reviewer needs both residual ratings and a Closure Reason to close a risk.

Figure 7. The Training Pavilion board shows its three states and flags one overdue mitigation action on the supplier risk.

Figure 8. Selecting East Wing keeps the site risks and hides the project-wide permit risk. The Monitoring column remains visible when empty.
Examine exposure in the Risk Matrix
- Open Risk Register → Risk Matrix. Start with All my projects or choose a project to narrow the matrix.
- Choose a Site after selecting a project. A site selection excludes project-wide risks. All sites and project-wide risks includes both.
- Choose Initial to review the original assessment or Residual to see the remaining exposure. The matrix includes risks in Open and Monitoring.
- Read likelihood down the left and impact across the top. Each cell shows the number of risks with those two ratings. The color marks the score band based on likelihood × impact.
- Click a populated cell to open the matching records in the register. In the residual view, click Unassessed residual risks to find risks that still need both residual ratings.

Figure 9. The initial assessment puts the East Wing supplier risk in the Likely × Severe cell. The other cells in this site scope are empty.

Figure 10. The residual Likely × Major cell opens the register filtered to the matching site and ratings.
Prepare and print a project review
- Open Risk Register → Project Review and select a project. Select a site to focus the summary on that part of the project.
- Use the counts to see how many risks are active, have high residual exposure, need assessment or review, or have overdue mitigation. Click a count to open the corresponding risks in the register.
- Read the three tables for the highest rated residual risks, overdue reviews, and overdue mitigation actions. Click a risk's name to open it. Each table shows up to ten entries. The count links open the full risk lists.
- Click Print PDF to download the review for the selected project and site. All totals and report rows follow the same access rules as the register. The summary reflects current records when printed.

Figure 11. The East Wing review lists the supplier risk and shows its overdue review and mitigation action.

Figure 12. The printable report includes the selected site, counts, and priority tables.
Record assessments and follow trends
- Open the risk and save the current ratings. Click Record Assessment. Odoo records the initial ratings and score, plus a residual entry when both residual ratings have been entered. The entries share a timestamp and preserve the site and the user who recorded them.
- Click Assessment History on the risk to see its recorded dates, ratings, scores, and recorder. History starts with the first capture. Changes to current ratings or site leave the earlier entries intact.
- Open Risk Register → Risk Trends. Use Project and Site to scope the chart. A site selection uses the site at the time each assessment was recorded. Use the search bar to focus on a particular risk or assessment date.
- Read each line as the daily average of saved scores for that assessment type. Multiple captures on the same day contribute to that day's average. The chart shows dates with at least one captured score. A gap means there was no score recorded for that series on that date. Switch to the list to see the individual entries behind those averages.

Figure 13. The supplier risk's history retains each recorded score, its timestamp, and who recorded it.

Figure 14. The East Wing chart shows a steady initial score and a residual score that falls from 12 to 6 across two assessments.
Escalate and review high residual risks
- An administrator selects the relevant company and opens Settings → PMIS Risk Management → Residual Risk Acceptance. Set High residual risk threshold to a value from 1 to 25. It defaults to 15 and includes the threshold itself. The register's High Residual Exposure filter and Project Review use this setting.
- Give at least one member of the project's Risk Team the PMIS Risk Reviewer role. Reviewers need access to the project's company.
- An authorized project member saves both residual ratings. When the score meets the threshold, click Request Acceptance. Odoo notifies eligible project reviewers through their configured Odoo notification channel and changes Residual Acceptance to Pending Review. Use the Pending Acceptance filter in the register to find open requests.

Figure 15. The supplier risk meets the company threshold of 12. Its request appears in Acceptance History with the captured score and threshold.
- As an authorized reviewer, open the risk and click Review Acceptance. Choose Accept or Decline, enter your reasoning, and click Record Decision. Odoo notifies eligible requesters and risk owners.

Figure 16. The reviewer can see the residual score and threshold that were in effect when the request was made.
- Open Acceptance History to see the decision, reviewer, time, and reason. Acceptance allows a reviewer to close the high residual risk using the normal Closure Reason. After a decline, address the concerns and submit another request when ready.

Figure 17. The recorded acceptance remains visible alongside the original request details.
Changing the residual ratings or site invalidates the current request or decision. Earlier decisions remain in Acceptance History, and pending requests are marked Superseded. Submit a new request if the updated risk still meets the threshold. Closing a risk below a newly raised threshold also marks its pending request Superseded. The matrix keeps its fixed score bands for visual comparison across projects and companies.
Record a materialized risk and its follow-up
- Open the risk from the register or board and choose Record Materialization. If the risk is closed, a reviewer reopens it first.
- Enter Occurred On and Actual Outcome. Describe what happened and the actual impact.
- Under Linked Follow-up, choose Issue or Corrective Action. Add a title, assign an eligible member of the project's Risk Team, and set a due date. Click Record Outcome.
- The risk now shows a Materialized badge. Open Materialization Outcome to see what happened, the site at the time of recording, who recorded it, and the linked follow-up. Use the register's Materialized filter to find these risks.

Figure 18. The recorded panel delivery delay is linked to an issue assigned to reschedule the installation crew.
- Click Follow-up Actions and open the issue or corrective action. When the work is complete, enter Completion Evidence, select Done, and save. Use New on the follow-up list to add further issue or corrective records for this outcome.

Figure 19. The linked issue keeps its risk and outcome references after the crew schedule is confirmed.
Each risk has one recorded materialization outcome. The outcome and follow-ups use the same project and company access rules as the risk. The standard risk closure and residual acceptance rules still apply.
Link an existing OCA record
- Open a materialized risk and click Materialization Outcome.
- Click Link Existing OCA Record. Odoo offers Helpdesk Ticket when OCA Helpdesk Management is installed and you can read its tickets. It offers Management System Corrective Action when that addon is installed and you can read its actions.
- Choose a record type, search for the existing record, and click Link Record. Select a record in the outcome's company. Management System results are limited to the Corrective Action response type.
- Check Ticket Status and Corrective Action Status under Linked OCA Records. Each status shows whether the record is open or closed and names its current stage. Reopen or refresh the outcome to see changes made in Helpdesk or Management System.
- Use the Open buttons to view the source records. Each outcome can hold one link of each type. To replace an existing link, select another record of that type while you have access to the current link.

Figure 20. The outcome shows the current stage and open status of both linked records.

Figure 21. Open Helpdesk Ticket takes the project user to the original ticket and its Helpdesk details.

Figure 22. Open Corrective Action opens the existing action in Management System.
Project and company rules continue to govern the outcome and its local follow-ups. Each OCA link is visible only to users who can read its source record. If you can read the record and lack access to its stage, the outcome shows Status Unavailable. Opening the native Management System form also requires access to its action stages, which the Management System User role provides.
Review follow-ups before closing a risk
- As a risk reviewer, check Materialization Outcome for unfinished local issues or corrective actions and the status of linked OCA records.
- On the risk form, change State to Closed. A warning appears if local follow-ups are unfinished, an OCA follow-up you can read is open, or you can read a linked record but cannot verify its stage.
- Acknowledge the warning. To keep the risk open while work continues, discard the change. To proceed, enter the Closure Reason and save. High residual risks still require reviewer acceptance before closure.

Figure 23. The closure warning appears as soon as the reviewer selects Closed, before the risk is saved.