PMISuite Commitment and Release Governance Pilot

License LGPL-3 Odoo 18.0

Use this guide to enroll a draft quotation and a planned rollout wave for one PMIS project. G2 governs the quotation confirmation and capacity commitment. G4 governs scaling the wave. G5 records who takes over day-to-day operations, what work remains, and how the measured benefits compare with their targets.

Slovenščina

Illustrated user manual

Roles and access

Install PMISuite Commitment and Release Governance in Apps. The addon depends on Odoo Sales and Mail and on the PMIS assessment, Change, and Risk addons. Give users the native project, Sales, Change, or Risk permissions they need to work with the linked records. Use the same company for the pilot, quotation, and Change initiative.

  • PMIS Governance Manager creates pilots, enrolls targets, and configures authority grants, capacity pools, and G4 guardrails. The manager can see pilots in the companies they have selected.

  • PMIS Governance User works on pilots where they are the owner, finance reviewer, or a listed participant. Name the internal users responsible for submitting evidence, deciding, verifying conditions, and taking over work.

  • Delegated approver records the G2 or G4 decision under an active grant for that pilot and gate type. A different user must decide a submission. The finance reviewer named on the pilot signs off G2 and must also be someone other than the G2 submitter.

  • An internal Sales user confirms the quotation. The Change sponsor authorizes the Change pilot, scales the wave, and prepares G5. The named operational owner accepts G5. Give the owner PMIS Change User access if they will record the benefit review. The sponsor can also record it.

Configure the pilot

  1. Open Commitment and Release Governance → Pilots. Create an active pilot with a company, project, objective, owner, finance reviewer, and participants. Include the sponsor, delegates, and operational assignees in the pilot roles or participant list.

  2. Under Decision Gates, create one G2 · Commitment for the draft quotation and one G4 · Release for the planned wave. The quotation's opportunity and the wave's Change initiative must both link to the pilot project. Enroll both targets before confirming or scaling.

  3. Under Authority Grants, grant each approver the relevant gate type for this pilot. Set Valid From and, if applicable, Valid Until. Set the G2 Commitment Limit in company currency. It must cover the quotation total including tax, converted to company currency.

  4. Under Capacity Pools, register the resource pool, company, period start, and available capacity in hours. For example, give the installation team 100 hours for the period if the quotation will need 70 hours.

  5. On G2, select the project risks that require acceptance under Required Project Risk Acceptances. The manager needs PMIS Risk User access to see this field. On G4, select at least one original control test from the pilot project under Mandatory Release Control Tests. Add workload and quality limits with Workload and Quality Guardrails. Set each unit, threshold, and direction (At Most or At Least), and mark blocking limits Mandatory. For example, require at most 30 support hours per week and at least 95% successful quality checks.

Record and verify decisions

  1. In Evidence Revisions, create a revision for the gate. Enter a title, the revision number, and a summary of the supporting evidence. Saving submits the revision and records the current source evidence. Use a higher revision number to submit corrected or changed evidence.

  2. The delegated approver opens My Decisions → Pending Approvals and selects Record Decision on the current revision. Enter the rationale and choose Approve, Approve with Conditions, or Reject.

  3. For conditional approval, enter each required action, its deadline, and two different users as owner and verifier. The owner records evidence in Approval Conditions or My Decisions → Assigned Conditions. The designated verifier opens the condition and selects Verify Evidence. Every condition must be verified by its deadline before execution. If a deadline is missed or the revision is rejected, submit a new revision and obtain a new decision.

Governance on an enrolled quotation or wave opens its gate. Decision History shows decisions across its evidence revisions.

Run G2 and confirm the quotation

  1. In Risk, obtain current acceptances for the risks required on the gate before saving the G2 revision. The revision captures the accepted records. Confirmation blocks if a required acceptance is missing, expired, or superseded. Obtain current acceptances and submit a fresh revision when the captured records differ.

  2. When creating the G2 revision, add Capacity Requirements for each pool and period with the hours needed. Under G2 Finance Review, enter forecast direct cost, margin assumptions, peak cash requirement, and cash assumptions, including when suppliers are paid and customers pay.

  3. Obtain the G2 decision and verify any conditions. On the current revision, the named finance reviewer checks untaxed revenue, forecast contribution and margin, and cash assumptions, then uses Record Finance Sign-off and enters the rationale.

  4. As a Sales user, open the quotation and select Confirm. Odoo checks the current approval and authority, quotation evidence, risk acceptances, finance sign-off, and remaining capacity. A successful confirmation uses the decision and commits the approved hours. If evidence changes, submit and approve a fresh revision and obtain its finance sign-off.

Run G4 and scale the rollout wave

  1. Open Change Initiatives and select the initiative linked to the pilot project. Under Readiness, record readiness checks and their evidence, and resolve all critical checks. The sponsor uses Record Sponsor Decision to Authorize Pilot. In Adoption Metrics, enter the measured adoption for the wave's cohort. The latest measurement for each metric name in that cohort must meet its target.

  2. For each listed control test, check the current result. An original test with no corrective retest must pass with evidence. When there is a corrective retest, the latest retest must pass with evidence and reviewer sign-off.

  3. Open each G4 guardrail and use Record Observation to enter a dated measurement and its evidence in the configured unit. Every active mandatory guardrail needs an observation within its threshold before scale-up.

  4. Save the G4 evidence revision and obtain the G4 decision and any condition verifications. On the wave, the sponsor selects Record Rollout Decision, chooses Scale, and records the rationale and evidence. Odoo revalidates readiness, adoption, control tests, and mandatory guardrail observations. If evidence fails or changes after submission, address the blocker, then submit a new revision and obtain a new approval before scaling. A successful scale marks the G4 decision as executed.

Run G5 and review measured benefits

  1. On the scaled wave, the sponsor opens Operational Handover and creates the handover. Name the operational owner and set the Benefit Review Date to today or later. List any outstanding actions with their owners and due dates. Use eligible pilot participants for these assignments.

  2. The operational owner selects Accept Handover before the review date passes. The accepted plan is fixed. Outstanding actions may remain open at acceptance. Each assigned owner uses Complete after finishing a transferred action.

  3. On the same Change initiative, open Benefits. Record the benefit owner, unit, direction, baseline, target, target date, and measurement method. Enter the measurement date, actual value, and supporting evidence. Include any attribution needed to explain the result.

  4. On the accepted handover, the operational owner or sponsor selects Record Benefit Review, selects the measured benefit from that initiative, and enters findings. Odoo preserves the measurement and evidence with the review and records whether the target was met. For example, a reduction from 12 to 7 incidents per month meets a target of 8 per month when lower is better.

  5. When ready to close the Change initiative as completed, the sponsor uses Close Initiative. Complete the native closure checks first. These include resolving all waves, recording a sustainment review for each scaled wave, and measuring at least one benefit. Every enrolled scaled wave must also have an accepted handover for its current scale decision. Transferred actions can remain open after closure.

Monitor the pilot

  • My Decisions shows pending approvals, assigned conditions, overdue blockers, and upcoming or overdue benefit reviews. The hourly scheduled action creates pending approval activities and condition reminders starting 48 hours before the deadline. It reminds the owner until evidence is provided, then the verifier. Benefit reminders for accepted handovers on current scaled waves start two calendar days before the review date in the assignee's timezone. They go to the eligible operational owner or, if needed, the eligible sponsor. The first recorded review clears the reminder for that handover.

  • Open Pilots → Dashboard for the pilot and select Refresh after a workflow change. For a completed walkthrough, look for Confirmed at G2, Scaled at G4, and Benefit Review Recorded at G5. Check Open Blockers for items still preventing execution and Benefit Outcomes for the latest reviewed measurement per benefit in the pilot. Open actions remain visible on the G4 and G5 tab until their assignees complete them.

Bug Tracker

Report issues through the PMISuite Operations issue tracker.

Credits

Authors

Luxim, Matmoz, and PMISuite.

Contributors

The Operations repository records contributions in its revision history.

Maintainers

Use the Operations issue tracker to contact the project team.